Managing Projects with Microsoft Project 2013

Question No: 41

You are managing a project using Project Professional 2013.

Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations.

You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.

What should you do?

  1. Click the BA1 resource and scroll to the end of the project.

  2. Click View, check Details, select Resource Form then click on the BA1 resource.

  3. Click View, check Details, select Task Form then click on the BA1 resource.

  4. Right-click the BA1 resource and select Information.

Answer: B

Question No: 42

You are a project manager, and you successfully complete a server consolidation project for one of your data centers. You use Project Standard 2013 to plan and track the work.

Your manager wants you to begin similar projects on two other data centers. You need to create a template based on the plan you used to manage the first data center consolidation project.

You need to ensure that the template has all baseline and actual data values removed. What should you do?

  1. Within Microsoft Windows Explorer, create a copy of the original project plan and rename the file type from .mpp to .mpt.

  2. Open the plan and use the Move Project button to set the start date to the start of the new project. Save the project file as Template.mpp.

  3. Open the plan and reset the percent complete for each task to 0. Save the file as Template.mpp.

  4. Open the plan and save the plan as a Project Template.

  5. Open the plan, and copy and paste all of the task information into a new plan. Save the plan as a Project Template.

Answer: D

Question No: 43

You manage a project by using Project Professional 2013. Your project is updated with changes to the baseline for selected tasks.

You back up your project fife before you start your next tracking cycle. After completing the tracking cycle, you notice that the baseline duration values on some of the summary tasks are not correct.

You need to correct these values before re-entering the tracking data. You open the backed up version of the project schedule.

What should you do next?

  1. Manually update the summary tasks with the new duration values.

  2. Reset the summary tasks to manual scheduling.

  3. Ensure the tasks durations are of the same denomination values. Then reenter the tracking data.

  4. Reset the baseline checking the Roll up baselines to all summary tasks option. Then reenter the tracking data.

Answer: D

Question No: 44

You are a project manager who uses Microsoft Excel 2013.

Your company decides to migrate all of the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all employees to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks with duration in days, and resources have been assigned and named. You have a status meeting in two days.

You need to provide your project#39;s information by using Project Professional 2013. What should you do?

  1. Create a new project plan in Project Professional 2013 and use the Gantt Chart Wizard to import from an Excel Workbook.

  2. Rename the Excel file from .xlsx to .mpx, and open it by using Project Professional 2013, activating the Mapping Excel Workbook feature. Map tasks, durations, and resources assigned into Microsoft Project fields.

  3. Open the Excel File .xlsx directly from Project Professional 2013, which will convert and map tasks, durations, and resources assigned into Project fields.

  4. Create a VBA macro by using the Excel Record Macro feature to import all tasks, durations, and resources assigned from Excel into your new Project Professional 2013 project plan.

Answer: C

Question No: 45

You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks.

You create two manually scheduled tasks and link them in a Finish to Start relationship. The project team member asks you to increase the duration of the predecessor task.

You notice that the successor task start date is now before the finish date of the predecessor task.

You want the successor task to start after the predecessor finishes. What should you do?

  1. Select both tasks and click Unlink.

  2. Select the successor task and click Mark on Track.

  3. Select the predecessor task and click Respect Links.

  4. Select the successor task and click Respect Links.

Answer: D

Question No: 46

You are a senior project manager, and your organization uses Project Standard 2013.

You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability.

You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours.

What should you do?

  1. Change the part-time resources#39; tasks to manually scheduled to ensure the dates do not go past the agreed-upon terms of their contract.

  2. Enter the availability start and end dates for each resource and change the percent of units to the agreed-upon amount in their contract.

  3. Enter the availability start and end dates for each resource and change the working time for each resource to only include days and hours agreed upon in their contract.

  4. Change the part-time resources#39; units to the percentage they are available and set task constraints to must finish on to ensure the dates do not go past the agreed-upon terms of their contract.

Answer: C

Question No: 47

You are a project manager for a company that uses baselines in Project Standard 2013.

Project stakeholders approve an update to the baseline of a project in progress. You enter the new tasks necessary to include the project schedule changes.

You need to update the baseline for the new tasks. What should you do?

  1. Delete the current baseline and re-baseline the entire project.

  2. Copy the current schedule to the baseline1 fields.

  3. Select the new tasks and copy the schedule to the baseline1 fields for the selected tasks.

  4. Select the new tasks and set the baseline for the selected tasks.

Answer: D

Question No: 48

You are a project manager for a software development company that uses Project Professional 2013.

For managing projects, your company has its own specialized processes, all of which you are familiar with, except for the reporting processes. Additionally, your company#39;s status reports of project progress are based on Work and Cumulative Work.

Thirty minutes before a meeting is scheduled to begin, the president of your company asks you to present the status report at the meeting.

You need the report to show all project tasks, resources assigned, and their respective Work and Cumulative Work on a monthly basis.

What should you do?

  1. Select the Gantt Chart view that has all project tasks and resources assigned. Click Add New Column to add Work and Cumulative Work. Go to the Gantt chart and adjust the timescale by zooming in or out to fit the monthly basis.

  2. Select the Gantt Chart view that has all project tasks and resources assigned. Right- click on the Gantt chart, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit the monthly basis.

  3. Select the Task Usage view that has all project tasks and resources assigned. Right- click the Details table, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit the monthly basis.

  4. Select the Network Diagram View. Choose Format Box Styles and add Cumulative Work to the Critical Task Box style.

Answer: C

Question No: 49

While creating a schedule with Project Professional 2013, you notice that there is a three- day duration on the Database Design task.

After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished.

You need to update the schedule with this information. What should you do?

  1. Reschedule uncompleted work for the project schedule.

  2. Add two days of actual duration and change the remaining duration for the task to zero.

  3. Update the task to show 100% completion on the ribbon bar.

  4. Enter a status date for the task.

Answer: B

Question No: 50

Your organization uses Project Professional 2013 and records actual hours worked on the project.

You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.

The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.

You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

  1. Open the Task Form and format it to show Work Details. Enter 25 hours of actual work for Resource1. Then save the changes.

  2. Open the Task Form and format it to show Work Details. Enter 75 hours of remaining work for the assigned resource. Then save the changes.

  3. Assign Resource2 and Resource3 to the task. Then save the changes.

  4. Open the Task Form and format it to show Work Details. Enter 33.33 hours of work for each resource. Then save the changes.

Answer: A,C

100% Ensurepass Free Download!
74-343 PDF
100% Ensurepass Free Guaranteed!
74-343 Dumps

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No


Leave a Reply

Your email address will not be published. Required fields are marked *

  • Categories

  • Tags

  • Hot Exams

  • Hot Exams

  • Hot Catageories

  • microsoft dumps

    62-193 Dumps
    70-243 Dumps
    70-246 Dumps
    70-247 Dumps
    70-331 Dumps
    70-332 Dumps
    70-333 Dumps
    70-334 Dumps
    70-339 Dumps
    70-341 Dumps
    70-342 Dumps
    70-345 Dumps
    70-346 Dumps
    70-347 Dumps
    70-348 Dumps
    70-354 Dumps
    70-355 Dumps
    70-357 Dumps
    70-383 Dumps
    70-384 Dumps
    70-385 Dumps
    70-398 Dumps
    70-410 Dumps
    70-411 Dumps
    70-412 Dumps
    70-413 Dumps
    70-414 Dumps
    70-417 Dumps
    70-461 Dumps
    70-462 Dumps
    70-463 Dumps
    70-464 Dumps
    70-465 Dumps
    70-466 Dumps
    70-467 Dumps
    70-469 Dumps
    70-470 Dumps
    70-473 Dumps
    70-475 Dumps
    70-480 Dumps
    70-481 Dumps
    70-482 Dumps
    70-483 Dumps
    70-484 Dumps
    70-485 Dumps
    70-486 Dumps
    70-487 Dumps
    70-488 Dumps
    70-489 Dumps
    70-490 Dumps
    70-491 Dumps
    70-492 Dumps
    70-494 Dumps
    70-496 Dumps
    70-497 Dumps
    70-498 Dumps
    70-499 Dumps
    70-517 Dumps
    70-532 Dumps
    70-533 Dumps
    70-534 Dumps
    70-535 Dumps
    70-537 Dumps
    70-640 Dumps
    70-642 Dumps
    70-646 Dumps
    70-673 Dumps
    70-680 Dumps
    70-681 Dumps
    70-682 Dumps
    70-684 Dumps
    70-685 Dumps
    70-686 Dumps
    70-687 Dumps
    70-688 Dumps
    70-689 Dumps
    70-692 Dumps
    70-694 Dumps
    70-695 Dumps
    70-696 Dumps
    70-697 Dumps
    70-698 Dumps
    70-703 Dumps
    70-705 Dumps
    70-713 Dumps
    70-734 Dumps
    70-735 Dumps
    70-740 Dumps
    70-741 Dumps
    70-742 Dumps
    70-743 Dumps
    70-744 Dumps
    70-745 Dumps
    70-761 Dumps
    70-762 Dumps
    70-764 Dumps
    70-765 Dumps
    70-767 Dumps
    70-768 Dumps
    70-773 Dumps
    70-774 Dumps
    70-775 Dumps
    70-776 Dumps
    70-778 Dumps
    70-779 Dumps
    70-980 Dumps
    70-981 Dumps
    70-982 Dumps
    74-343 Dumps
    74-344 Dumps
    74-409 Dumps
    74-678 Dumps
    74-697 Dumps
    77-418 Dumps
    77-419 Dumps
    77-420 Dumps
    77-421 Dumps
    77-422 Dumps
    77-423 Dumps
    77-424 Dumps
    77-425 Dumps
    77-426 Dumps
    77-427 Dumps
    77-428 Dumps
    77-600 Dumps
    77-601 Dumps
    77-602 Dumps
    77-603 Dumps
    77-604 Dumps
    77-605 Dumps
    77-725 Dumps
    77-726 Dumps
    77-727 Dumps
    77-728 Dumps
    77-729 Dumps
    77-730 Dumps
    77-731 Dumps
    77-853 Dumps
    77-881 Dumps
    77-882 Dumps
    77-883 Dumps
    77-884 Dumps
    77-885 Dumps
    77-886 Dumps
    77-887 Dumps
    77-888 Dumps
    77-891 Dumps
    98-349 Dumps
    98-361 Dumps
    98-362 Dumps
    98-363 Dumps
    98-364 Dumps
    98-365 Dumps
    98-366 Dumps
    98-367 Dumps
    98-368 Dumps
    98-369 Dumps
    98-372 Dumps
    98-373 Dumps
    98-374 Dumps
    98-375 Dumps
    98-379 Dumps
    98-380 Dumps
    98-381 Dumps
    98-382 Dumps
    98-383 Dumps
    98-388 Dumps
    AZ-100 Dumps
    AZ-101 Dumps
    AZ-102 Dumps
    INF-203x Dumps
    INF-204x Dumps
    INF-205x Dumps
    INF-206x Dumps
    MB2-700 Dumps
    MB2-701 Dumps
    MB2-702 Dumps
    MB2-703 Dumps
    MB2-704 Dumps
    MB2-706 Dumps
    MB2-707 Dumps
    MB2-708 Dumps
    MB2-709 Dumps
    MB2-710 Dumps
    MB2-711 Dumps
    MB2-712 Dumps
    MB2-713 Dumps
    MB2-714 Dumps
    MB2-715 Dumps
    MB2-716 Dumps
    MB2-717 Dumps
    MB2-718 Dumps
    MB2-719 Dumps
    MB2-877 Dumps
    MB5-705 Dumps
    MB6-700 Dumps
    MB6-701 Dumps
    MB6-702 Dumps
    MB6-703 Dumps
    MB6-704 Dumps
    MB6-705 Dumps
    MB6-884 Dumps
    MB6-885 Dumps
    MB6-886 Dumps
    MB6-889 Dumps
    MB6-890 Dumps
    MB6-892 Dumps
    MB6-893 Dumps
    MB6-894 Dumps
    MB6-895 Dumps
    MB6-896 Dumps
    MB6-897 Dumps
    MB6-898 Dumps