Managing Programs and Projects with Project Server 2013

Question No: 1

You work for an organization that uses Project Server 2013. Single-entry mode is disabled.

Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:

->During week one, a team member enters a total of 20 hours of actual work.

->During week two, the team member modifies the total to 30 hours of actual work.

->Following a save, the work value remains the same, and the remaining work value decreases.

->Additionally, the percent of work complete increases.

Which tracking method should you use?

  1. Percent of work complete

  2. Actual work done and work remaining

  3. Hours of work done per period

  4. Report hours worked every day

Answer: B

Question No: 2

You are a project manager who has standard permissions, and your organization uses Project Server 2013.

Some of your resources consistently update their assignments correctly. You want to accept their future updates without review.

You need to begin accepting their updates without review by using the least amount of effort possible.

What should you do?

  1. Set up a rule in the Approval Center to automatically accept ail updates, specifying the resources by name, for all projects.

  2. Set up a VBA macro to automatically accept all updates, specifying the resources by name, for all projects.

  3. Set up a Project Server 2013 workflow by using Microsoft SharePoint Designer to automatically accept all updates, specifying the resources by name, for all projects.

  4. Set up a timesheet event handler in the Project Server Settings to automatically accept all updates, specifying the resources by name, for all projects.

Answer: A

Question No: 3

You are a program manager who uses Project Server 2013 and Project Professional 2013. You have administrative rights.

Your project managers create subprojects for your program-level master project. You insert the subprojects into your master project file by using Project Professional 2013. You are unable to save the master project file.

You need to ensure that your master project file appears with its subprojects when you use the Project Web App (PWA).

What should you do?

  1. Create the master project file and add the subprojects while in PWA rather than in Project Professional 2013. Then publish to the server.

  2. Create your master project file and publish to the server.

  3. Create a custom view in the PWA to view the master projects.

  4. Turn on the allow master projects to be saved and published setting and publish to the server.

Answer: D

Question No: 4

You are a project manager who uses Project Server 2013.

You want to use the Resource Center Availability function and the Assignment Work by Resource view to see the proposed and active projects for a particular resource. However, you are only able to view part of the work load for the resource.

You need to view the complete work load for the resource.

Which two settings should you verify? (Each correct answer presents part of the solution. Choose two.)

  1. That Include proposed bookings is selected

  2. That the units chosen are correct

  3. That the date range is correct

  4. That the resource is selected on the Resource Availability view

Answer: C,D

Question No: 5

You are a project manager in an organization that uses Project Server 2013. You manage a project that has Baseline0 set. There are enterprise custom fields with formulas that make calculations by using the Baseline0 fields.

You are planning a major rescheduling in your project and intend to update the project baseline so the formulas in the enterprise custom fields take the new values of the baseline fields.

However, for future reference, you want to keep your original baseline. You need to update the project baseline without losing the original values. What should you do?

  1. Open you project in Project Professional 2013. In the Gantt chart view, include all the Baseline0 and Baseline1 fields. Copy and paste all values from Baseline0 to Baseline1. Set a new Baseline0, and save and publish the project.

  2. Open your project in Project Professional 2013 and copy Baseline0 into Baseline1. Set a new Baseline0, and save and publish the project.

  3. Open your project in Project Professional 2013 and set a new Baseline0. Project Professional will automatically copy the original Baseline0 into Baseline1. Save and publish the project.

  4. Open your project in Project Professional 2013, set a new Baseline1, and save and publish the project. Ask the Project Server administrator to change the enterprise custom fields so that they use the Baseline1 instead of Baseline0.

Answer: B

Question No: 6

You are a project manager for an organization that uses Project Server 2013.

After performing a review of all the risks created by your project team for one of your projects, you realize that the risks are not linked to their related tasks.

You need to link the risks to their related tasks. What should you do?

  1. Open each risk, select the Attach file option, and then select the name of the related task.

  2. Open your project in Project Web App (PWA). Highlight each task and use the Related Item option for linking one or more risks for each task.

  3. Create a new field for the Risk content type in SharePoint and name it quot;task namequot;. Then open each risk and write the name of the related task into the new field.

  4. Open each risk and copy and paste its name into the Notes field in the task page.

Answer: B

Question No: 7

You are a project manager in an organization that uses Project Server 2013. Project team members submit updates to tasks through Project Web App (PWA).

A project team member clicks Remove Task, and you approve it. You apply this change to the project.

The team member indicates that they only want to hide the task from that particular view, not remove the task permanently.

You need to ensure the task is returned to the Tasks page so it can be properly hidden. What should you do?

  1. Mark the task as active and publish the project.

  2. Tell the team member to choose Add Row and click Add Team Task.

  3. Tell the team member to modify the filter to show incomplete tasks.

  4. Assign the team member to the task and publish the project.

Answer: D

Question No: 8

You are the administrator of a Project Server 2013 environment.

You set up an enterprise custom resource field to define skill sets for resources. When trying to replace your generic resources, the matching function does not work.

You need to reconfigure Project Server 2013 to enable the skills match function. What should you do?

  1. Ensure that the resource is assigned to the correct department relative to the type of skills required.

  2. Define a supporting skills table and associate it to the enterprise resource custom field. When adding the table, ensure that you are using this field for matching generic resources.

  3. Use the Department table and associate it to the enterprise resource custom field you create for skills.

  4. Create an enterprise custom skills field for defining your resources#39; skills. Then use the Enterprise Resource Pool view alongside the Project Team view, and replace your resources with the required skillset.

Answer: B

Question No: 9

You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule.

You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks.

You check out your schedule in Project Web App (PWA) for editing and select the newly- added tasks.

What should you do next?

  1. Set an interim plan.

  2. Use an unused baseline to set a new baseline.

  3. Clear the baseline and then set a baseline for the entire project.

  4. Set a baseline for only the selected tasks.

Answer: B

Question No: 10

As a team member, you submit your timesheet for approval in Project Server 2013.

After sending the timesheet to the timesheet manager, you realize you forgot to include some work.

You need to ensure that the work is added to your timesheet.

What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

  1. Make an adjusting entry on your next timesheet and then submit that one.

  2. Re-open it immediately. Make your changes and re-send it.

  3. Recall the timesheet from the Manage Timesheets page. Make your changes and re- send it.

  4. Ask your timesheet manager to reject your timesheet. Make your changes and re-send it.

Answer: C,D

100% Ensurepass Free Download!
74-344 PDF
100% Ensurepass Free Guaranteed!
74-344 Dumps

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No


Leave a Reply

Your email address will not be published. Required fields are marked *

  • Categories

  • Tags

  • Hot Exams

  • Hot Exams

  • Hot Catageories

  • microsoft dumps

    62-193 Dumps
    70-243 Dumps
    70-246 Dumps
    70-247 Dumps
    70-331 Dumps
    70-332 Dumps
    70-333 Dumps
    70-334 Dumps
    70-339 Dumps
    70-341 Dumps
    70-342 Dumps
    70-345 Dumps
    70-346 Dumps
    70-347 Dumps
    70-348 Dumps
    70-354 Dumps
    70-355 Dumps
    70-357 Dumps
    70-383 Dumps
    70-384 Dumps
    70-385 Dumps
    70-398 Dumps
    70-410 Dumps
    70-411 Dumps
    70-412 Dumps
    70-413 Dumps
    70-414 Dumps
    70-417 Dumps
    70-461 Dumps
    70-462 Dumps
    70-463 Dumps
    70-464 Dumps
    70-465 Dumps
    70-466 Dumps
    70-467 Dumps
    70-469 Dumps
    70-470 Dumps
    70-473 Dumps
    70-475 Dumps
    70-480 Dumps
    70-481 Dumps
    70-482 Dumps
    70-483 Dumps
    70-484 Dumps
    70-485 Dumps
    70-486 Dumps
    70-487 Dumps
    70-488 Dumps
    70-489 Dumps
    70-490 Dumps
    70-491 Dumps
    70-492 Dumps
    70-494 Dumps
    70-496 Dumps
    70-497 Dumps
    70-498 Dumps
    70-499 Dumps
    70-517 Dumps
    70-532 Dumps
    70-533 Dumps
    70-534 Dumps
    70-535 Dumps
    70-537 Dumps
    70-640 Dumps
    70-642 Dumps
    70-646 Dumps
    70-673 Dumps
    70-680 Dumps
    70-681 Dumps
    70-682 Dumps
    70-684 Dumps
    70-685 Dumps
    70-686 Dumps
    70-687 Dumps
    70-688 Dumps
    70-689 Dumps
    70-692 Dumps
    70-694 Dumps
    70-695 Dumps
    70-696 Dumps
    70-697 Dumps
    70-698 Dumps
    70-703 Dumps
    70-705 Dumps
    70-713 Dumps
    70-734 Dumps
    70-735 Dumps
    70-740 Dumps
    70-741 Dumps
    70-742 Dumps
    70-743 Dumps
    70-744 Dumps
    70-745 Dumps
    70-761 Dumps
    70-762 Dumps
    70-764 Dumps
    70-765 Dumps
    70-767 Dumps
    70-768 Dumps
    70-773 Dumps
    70-774 Dumps
    70-775 Dumps
    70-776 Dumps
    70-778 Dumps
    70-779 Dumps
    70-980 Dumps
    70-981 Dumps
    70-982 Dumps
    74-343 Dumps
    74-344 Dumps
    74-409 Dumps
    74-678 Dumps
    74-697 Dumps
    77-418 Dumps
    77-419 Dumps
    77-420 Dumps
    77-421 Dumps
    77-422 Dumps
    77-423 Dumps
    77-424 Dumps
    77-425 Dumps
    77-426 Dumps
    77-427 Dumps
    77-428 Dumps
    77-600 Dumps
    77-601 Dumps
    77-602 Dumps
    77-603 Dumps
    77-604 Dumps
    77-605 Dumps
    77-725 Dumps
    77-726 Dumps
    77-727 Dumps
    77-728 Dumps
    77-729 Dumps
    77-730 Dumps
    77-731 Dumps
    77-853 Dumps
    77-881 Dumps
    77-882 Dumps
    77-883 Dumps
    77-884 Dumps
    77-885 Dumps
    77-886 Dumps
    77-887 Dumps
    77-888 Dumps
    77-891 Dumps
    98-349 Dumps
    98-361 Dumps
    98-362 Dumps
    98-363 Dumps
    98-364 Dumps
    98-365 Dumps
    98-366 Dumps
    98-367 Dumps
    98-368 Dumps
    98-369 Dumps
    98-372 Dumps
    98-373 Dumps
    98-374 Dumps
    98-375 Dumps
    98-379 Dumps
    98-380 Dumps
    98-381 Dumps
    98-382 Dumps
    98-383 Dumps
    98-388 Dumps
    AZ-100 Dumps
    AZ-101 Dumps
    AZ-102 Dumps
    INF-203x Dumps
    INF-204x Dumps
    INF-205x Dumps
    INF-206x Dumps
    MB2-700 Dumps
    MB2-701 Dumps
    MB2-702 Dumps
    MB2-703 Dumps
    MB2-704 Dumps
    MB2-706 Dumps
    MB2-707 Dumps
    MB2-708 Dumps
    MB2-709 Dumps
    MB2-710 Dumps
    MB2-711 Dumps
    MB2-712 Dumps
    MB2-713 Dumps
    MB2-714 Dumps
    MB2-715 Dumps
    MB2-716 Dumps
    MB2-717 Dumps
    MB2-718 Dumps
    MB2-719 Dumps
    MB2-877 Dumps
    MB5-705 Dumps
    MB6-700 Dumps
    MB6-701 Dumps
    MB6-702 Dumps
    MB6-703 Dumps
    MB6-704 Dumps
    MB6-705 Dumps
    MB6-884 Dumps
    MB6-885 Dumps
    MB6-886 Dumps
    MB6-889 Dumps
    MB6-890 Dumps
    MB6-892 Dumps
    MB6-893 Dumps
    MB6-894 Dumps
    MB6-895 Dumps
    MB6-896 Dumps
    MB6-897 Dumps
    MB6-898 Dumps