Managing Programs and Projects with Project Server 2013

Question No: 41

You are a project manager who uses Project Server 2013.

You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.

You need to replace this resource with a newly-hired resource. What should you do?

  1. Open the project in Project Professional 2013. Go to the Resource Sheet view and add the new resource. Then replace the resource assignment in the Assignment view with the new resource.

  2. Open the project in Project Web App (PWA) and manually edit the resource in the Gantt view.

  3. Open the project in Project Professional 2013. Edit the project, build the team, and then select the resource to add and the resource to replace. Then click Replace.

  4. Open the project in Project Professional 2013 and manually edit the resource in the Gantt view.

Answer: C

Question No: 42

Your work in a multinational corporation which uses Project Server 2013 to plan and control projects in different business units. Each business unit has its own portfolio of projects but can participate in strategic projects. The Project Management Office (PMO) has configured Enterprise Project Types (EPTs) to create new products, launch marketing campaigns, and deploy new lines of business tools to comply with the governance processes.

One of your roles is to identify new products. A local team in Singapore produces an effective idea for a new product.

You need to create a business case for the next portfolio analysis. You need to gather general information about the new product by efficiently collaborating with the local team.

What should you do?

  1. Start a Project with the New Product EPT, which will trigger a workflow and allow you to display and collect descriptive data and exchange information in the Project site.

  2. Exchange information by sharing documents through SkyDrive Pro 2013.

  3. Create a Team Site for the Singapore business unit for gathering information and assigning tasks. Save the Team Site as a template for use within the New Product EPT.

  4. Start a new enterprise project with the Microsoft SharePoint task list EPT, and grant immediate access to the team so they can share information, assign tasks, and collaborate.

Answer: A

Question No: 43

Your organization uses Project Server 2013. For security reasons, only individuals inside your organization have access to Project Web App (PWA).

You want to keep track of progress made by a third-party vendor. The vendor will email task progress to the resource manager. The resource manager will be responsible for

reporting vendor progress back to the project manager in PWA. You need to enable this functionality.

You add the vendor as a resource in Project Server. What should you do next?

  1. Assign the resource manager as the Status Manager.

  2. Assign the project manager as the Assignment Owner.

  3. Assign the resource manager as the Assignment Owner.

  4. Assign the administrator as the Status Manager.

Answer: C

Question No: 44

You are a project manager, and your organization uses Project Server 2013 with an enterprise resource pool.

After assigning resources, you discover that two of them are showing up as overallocated. These two resources also work on other projects that you cannot change.

You need to solve this problem. What should you do?

  1. Change the project priority level of your project to 1000 so that it becomes the highest priority and will be automatically leveled.

  2. Open your Project Plan in Project Professional 2013 and level the resources.

  3. Open all Project Plans in Project Web App (PWA) as a temporary master plan and level all resources.

  4. Open all Project Plans in Project Professional 2013 and level all resources.

Answer: B

Question No: 45

You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Project Site Provisioning Mode for your organization allows users to choose when to provision project sites.

You use Project Web App (PWA) to create a new enterprise project named Sub1 that will be inserted as a subproject in your existing master project named Master.

You need to create a new project site for Sub1 as a subsite of the existing Master Project Site.

What should you do?

  1. Open the Sub1 project for editing in PWA, click the Project Site button, and provision the Sub1 site under the Master Project Site.

  2. Open the Master project in Project Professional 2013, insert Sub1 as a subproject, publish, and provision the Sub1 site under the Master Project Site.

  3. Open the Sub1 project for editing in PWA, publish, and provision the Sub1 site under the Master Project Site.

  4. Open the Sub1 project in Project Professional 2013, publish, and provision the Sub1 site under the Master Project Site.

    Answer: D

    Question No: 46 HOTSPOT

    A company has established these three business drivers for a Portfolio Analysis:

    1. Improve Customer Satisfaction

    2. Increase Market Share

    3. Standardize Processes

      The board of directors plans to perform a pairwise comparison to prioritize the business drivers.

      After the board of directors sets two out of the three priorities, you realize you can finish the job.

      You need to ensure that the consistency ratio of the final outcome is 100%.

      What should you do? (To answer, configure the appropriate option in the dialog box in the answer area.)

      Ensurepass 2018 PDF and VCE

      Ensurepass 2018 PDF and VCE

      Answer:

      Ensurepass 2018 PDF and VCE

      Explanation:

      Ensurepass 2018 PDF and VCE

      C:\Pasban Work\Cert Paper Exams\Microsoft\74-344\5a.JPG

      Question No: 47

      You are a program manager in an organization that uses Project Server 2013. The allow master projects to be saved and published function is not enabled.

      Your program contains seven active projects managed in Project Online.

      You need a way to review the tasks flagged as milestones in all seven active projects at one time.

      You open Project Center in Project Web App (PWA). What should you do next?

      1. Select all seven projects and choose Export to Excel on the ribbon.

      2. Select all seven projects, open in a temporary master project, expand all tasks, and filter for milestone tasks.

      3. Select the Subprojects check box on the ribbon.

      4. Create a custom filter in which the Milestone field equals Yes, and apply it to the view.

Answer: B

Question No: 48

You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.

You notice that some projects have been published with incorrect data. You and the project managers spend a lot of time correcting the data problems.

You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:

->Review the project data after the project managers create the projects.

->Send the projects back to the project managers if you find incorrect data so that they can make the appropriate corrections.

->Repeat the data verification process unless the data does not have any errors.

->Publish a project only when all of its data is correctly completed.

What should you do?

  1. Instruct the project managers to include a task named project review every time they create a project and assign it to you. Project Server will notify you about the project creation. If you find an error, delete the project, and the project manager should create the project again.

  2. Instruct the project managers to send you an email every time they create a project they need so that you can review the project. If you find an error, delete the project, and the project manager should create the project again.

  3. Create a new workflow that automates all of the requirements. Create a new enterprise project type and link it with the workflow.

  4. Create a Published event handler that automates all of the requirements for this enterprise project type.

Answer: C

Question No: 49

You are a program manager for an organization that uses Project Server 2013.

You work in a master project, which contains ten sub-projects. One of your project managers makes changes to a sub-project and publishes it.

You open the master project and realize that these changes are not reflected in the master project schedule.

You need to ensure these changes are reflected in the master project. What should you do?

  1. Open the master project in Project Web App (PWA), click on the Calculate Project to calculate all changes, and then publish.

  2. Open the master project in Project Professional 2013, click on the Calculate Project to calculate all changes, and then publish.

  3. Open the master project in Project Professional 2013, expand all sub-projects, and then publish.

  4. Open the master project in Project Web App (PWA), expand all sub-projects, and then publish.

Answer: C

Question No: 50

You are a project manager for an organization that uses Project Server 2013. When you publish a new schedule, a default Project Site is created for you.

A team member asks you to create a task list separately from the schedule. The team member wants to use the list for specific work they need to perform in order to complete one of the assignments in the project schedule.

On your Project Site, you have the tasks that they have asked for in a task list. The work

being performed by this team member becomes critical to the success of your overall schedule.

Management asks for a simple report showing them the task list in an easy-to-read format. You need to implement this request.

What should you do?

  1. In Project Web App (PWA), open the schedule and export the task list to Microsoft Excel. Add the tasks to the Pivot Chart for management to view.

  2. In Project Web App (PWA), open the schedule and add the tasks to the Timeline for management to view.

  3. In your Project Site, open the task list and add the tasks to the Timeline for management to view.

  4. In your Project Site, open the task list and export it to Microsoft Excel. Add the tasks to the Pivot Chart for management to view.

Answer: C

100% Ensurepass Free Download!
74-344 PDF
100% Ensurepass Free Guaranteed!
74-344 Dumps

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No


Leave a Reply

Your email address will not be published. Required fields are marked *

  • Categories

  • Tags

  • Hot Exams

  • Hot Exams

  • Hot Catageories

  • microsoft dumps

    62-193 Dumps
    70-243 Dumps
    70-246 Dumps
    70-247 Dumps
    70-331 Dumps
    70-332 Dumps
    70-333 Dumps
    70-334 Dumps
    70-339 Dumps
    70-341 Dumps
    70-342 Dumps
    70-345 Dumps
    70-346 Dumps
    70-347 Dumps
    70-348 Dumps
    70-354 Dumps
    70-355 Dumps
    70-357 Dumps
    70-383 Dumps
    70-384 Dumps
    70-385 Dumps
    70-398 Dumps
    70-410 Dumps
    70-411 Dumps
    70-412 Dumps
    70-413 Dumps
    70-414 Dumps
    70-417 Dumps
    70-461 Dumps
    70-462 Dumps
    70-463 Dumps
    70-464 Dumps
    70-465 Dumps
    70-466 Dumps
    70-467 Dumps
    70-469 Dumps
    70-470 Dumps
    70-473 Dumps
    70-475 Dumps
    70-480 Dumps
    70-481 Dumps
    70-482 Dumps
    70-483 Dumps
    70-484 Dumps
    70-485 Dumps
    70-486 Dumps
    70-487 Dumps
    70-488 Dumps
    70-489 Dumps
    70-490 Dumps
    70-491 Dumps
    70-492 Dumps
    70-494 Dumps
    70-496 Dumps
    70-497 Dumps
    70-498 Dumps
    70-499 Dumps
    70-517 Dumps
    70-532 Dumps
    70-533 Dumps
    70-534 Dumps
    70-535 Dumps
    70-537 Dumps
    70-640 Dumps
    70-642 Dumps
    70-646 Dumps
    70-673 Dumps
    70-680 Dumps
    70-681 Dumps
    70-682 Dumps
    70-684 Dumps
    70-685 Dumps
    70-686 Dumps
    70-687 Dumps
    70-688 Dumps
    70-689 Dumps
    70-692 Dumps
    70-694 Dumps
    70-695 Dumps
    70-696 Dumps
    70-697 Dumps
    70-698 Dumps
    70-703 Dumps
    70-705 Dumps
    70-713 Dumps
    70-734 Dumps
    70-735 Dumps
    70-740 Dumps
    70-741 Dumps
    70-742 Dumps
    70-743 Dumps
    70-744 Dumps
    70-745 Dumps
    70-761 Dumps
    70-762 Dumps
    70-764 Dumps
    70-765 Dumps
    70-767 Dumps
    70-768 Dumps
    70-773 Dumps
    70-774 Dumps
    70-775 Dumps
    70-776 Dumps
    70-778 Dumps
    70-779 Dumps
    70-980 Dumps
    70-981 Dumps
    70-982 Dumps
    74-343 Dumps
    74-344 Dumps
    74-409 Dumps
    74-678 Dumps
    74-697 Dumps
    77-418 Dumps
    77-419 Dumps
    77-420 Dumps
    77-421 Dumps
    77-422 Dumps
    77-423 Dumps
    77-424 Dumps
    77-425 Dumps
    77-426 Dumps
    77-427 Dumps
    77-428 Dumps
    77-600 Dumps
    77-601 Dumps
    77-602 Dumps
    77-603 Dumps
    77-604 Dumps
    77-605 Dumps
    77-725 Dumps
    77-726 Dumps
    77-727 Dumps
    77-728 Dumps
    77-729 Dumps
    77-730 Dumps
    77-731 Dumps
    77-853 Dumps
    77-881 Dumps
    77-882 Dumps
    77-883 Dumps
    77-884 Dumps
    77-885 Dumps
    77-886 Dumps
    77-887 Dumps
    77-888 Dumps
    77-891 Dumps
    98-349 Dumps
    98-361 Dumps
    98-362 Dumps
    98-363 Dumps
    98-364 Dumps
    98-365 Dumps
    98-366 Dumps
    98-367 Dumps
    98-368 Dumps
    98-369 Dumps
    98-372 Dumps
    98-373 Dumps
    98-374 Dumps
    98-375 Dumps
    98-379 Dumps
    98-380 Dumps
    98-381 Dumps
    98-382 Dumps
    98-383 Dumps
    98-388 Dumps
    AZ-100 Dumps
    AZ-101 Dumps
    AZ-102 Dumps
    INF-203x Dumps
    INF-204x Dumps
    INF-205x Dumps
    INF-206x Dumps
    MB2-700 Dumps
    MB2-701 Dumps
    MB2-702 Dumps
    MB2-703 Dumps
    MB2-704 Dumps
    MB2-706 Dumps
    MB2-707 Dumps
    MB2-708 Dumps
    MB2-709 Dumps
    MB2-710 Dumps
    MB2-711 Dumps
    MB2-712 Dumps
    MB2-713 Dumps
    MB2-714 Dumps
    MB2-715 Dumps
    MB2-716 Dumps
    MB2-717 Dumps
    MB2-718 Dumps
    MB2-719 Dumps
    MB2-877 Dumps
    MB5-705 Dumps
    MB6-700 Dumps
    MB6-701 Dumps
    MB6-702 Dumps
    MB6-703 Dumps
    MB6-704 Dumps
    MB6-705 Dumps
    MB6-884 Dumps
    MB6-885 Dumps
    MB6-886 Dumps
    MB6-889 Dumps
    MB6-890 Dumps
    MB6-892 Dumps
    MB6-893 Dumps
    MB6-894 Dumps
    MB6-895 Dumps
    MB6-896 Dumps
    MB6-897 Dumps
    MB6-898 Dumps